May 16, 2024
May 20th - 24th
- Continue to install temportary water connections to properties.
- Start to fill/ chlorinate/ and sample the newly installed temp water main.
- Perform any test pits needed for field verifications.
** No Work after noon 5/24 or all day on 5/27 for Memorial Day **
May 28th - 31st
- Mill 1500’ of trench (if allowed) in preparation for water main install.
- Finish any temporary water ties as needed.
- Bacteria testing on temporary water main.
- Install caps on side streets if needed.
- Begin water main install on Squires Lane.
May 15, 2024
Pavement milling will take place on Thursday 5/16/2024 from Squires Lane to Pleasant Street.
Parking will be limited.
May 09, 2024
- May 13th-17th
-
- Mobilize equipment and materials.
- Set up staging areas and office trailers.
- Begin temporary water in Phase 3 (Squires Lane to Pleasant Street).
-
- Temporary water will be dug through driveways and side streets and graveled back in flush.
- Mainline water trench will be sawcut.
- May 20th-24th
-
- Continue installing temporary water.
- Property connections.
- Fill/chlorinate and sample the newly installed temporary water main.
- Perform test pits to field verify location of existing utilities.
May 06, 2024
Construction for the Main Street Project begins May 13, 2024.
The first Phase of the Project - Squires Lane to Pleasant Street
Weekly Updates will be found here!
May 06, 2024
Water Main Flushing
May 13, 2024 to June 21, 2024